Hardscape/Landscape/Site Package Contractor: Site Tech
Hardscape/Landscape Design: Magna International, Inc.
Owner: MEC Developments, Inc.
This massive hardscape, landscape & site lighting package was completed in only 90 days - from the Winner's Circle fountain excavation to project completion only hours prior to the park's grand opening festivities. Within 30 days of breaking ground, Site Tech began accelerating the construction schedule and finished the job with a grueling, 45-day around-the-clock sprint with second tier subs Vila & Son Landscape and Tri-City Electric, to ensure that the clubhouse and viewing stands were ready by race day.